Beatson Institute upgrade

Partager sur

Beatson Institute is one of Cancer Research UK’s core-funded institutes, with a reputation for basic cancer research, including world-class metabolism studies and renowned in vivo modelling of tumour growth and metastasis. Their goal for the future is for their discovery work to continue apace that is applied to preclinical and clinical studies. In order to achieve their future goals Beatson Institute needed their old inefficient Air Handling Unit (AHU) upgraded for their site in Glasgow.

 

6 week

programme

14 day

holding test

2

cleanrooms

Our Solution

As a cleanroom design and build specialist, Bouygues Energies & Services were appointed by Beatson Institute to supply an energy saving and flexible solution. A solution that would help improve the internal air quality, humidity, temperature control and air changes within two of their cleanrooms. 

Bouygues Energies & Services initially proposed two Air Handling Units to support their requirement, but later found that one unit would be sufficient. In return saving Beatson Institute money and space.  

The work was carried out within a tight space in their live facility where the timescales for a shutdown was of the upmost importance. This resulted in a phased approach where the existing AHU and associated elements were removed and the new AHU unit, associated controls along new supply and extract ductwork were installed using a flat-pack method. Finally a 14 day holding test was required, where it needed to demonstrate the environmental conditions could be maintained within set parameters for two weeks.   

The project was completed to a cGMP standard with the support of installation, mechanical, electrical and commissioning support from Bouygues Energies & Services. A 6 week programme completed on time and within budget.
 

Client Benefits 

Zero down time 
The site had minimal disruptions to the site allowing the client to operate to the same operational level and continue with their development. 

Delivered on time 
The client needed the project to be completed in a specific time frame allowing them to move forward with their future development. The project was completed in the estimated timeframe and within budget.
 

Latest case studies

0 1 2 3

Latest news

Find all the topics that make Bouygues Energies & Services news: projects, innovations, public and client events, partnerships, press releases ...

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267